Grantham Canal volunteers install new lock gates into historic lock

Volunteers on the Grantham Canal have installed new oak lock gates into the restored Lock 14 – the first new gates the lock has had in almost 90 years. 

The Canal & River Trust, Grantham Canal Society (GCS) and the Waterway Recovery Group have been working for the past two years to restore the formerly derelict lock near Stenwith. The restoration had been on hold for several months due to the coronavirus lockdown but, with restrictions easing, the team have wasted little time in getting the lock ready for its new gates. 

The new oak gates have been hand built at the Trust’s lock gate workshop at Stanley Ferry near Wakefield. Each of the bottom gates weighs 2.3 tonnes with the top gates weighing 1.1 tonnes each.  

The lock restoration is part of a project, which has been awarded a £830,500 grant from the National Lottery Heritage Fund, to bring locks 14 and 15 back into use. The project has already seen the full restoration of Lock 15 which last year welcomed its first boat since falling into dereliction in the 1920s.

Since 2018, the volunteers have been taking the crumbling walls down brick-by-brick, laying new foundations and rebuilding the walls by hand.

Karen Rice, project manager for the Canal & River Trust, says: “This is such a milestone in the long history of the canal and after the past few months it’s such a relief to finally get here.

“The volunteers have been amazing all the way through this project and it’s been so frustrating for everyone to put everything on hold. We’ve all been itching to get going and as soon as we got the green light to get back on site everyone’s been working flat out to make up for lost time and get the lock ready for its new gates. 

“It was such a special, historic moment to see the lock gates lifted in and caps an incredible five years in which we’ve seen two derelict locks brought back to life. It couldn’t have happened without the support of the National Lottery Heritage Fund and hard work of the volunteers and we’re so grateful for everything they’ve done.” 

Designed and built by renowned canal engineer William Jessop, the canal was opened in 1797 as a cheap way of transporting coal from Nottingham to Grantham. It proved prosperous until the opening of the Grantham to Nottingham railway in 1850. Unable to compete with the railway the canal eventually closed to boats in 1929. 

By the 1960s most of the locks on the canal were derelict and their lock gates replaced with concrete weirs to control the water levels. 

  As well as the physical works, the aim of the project is also to raise awareness of the canal’s build and natural heritage and encourage more people to explore it through walking trails, archaeological activities, on-site information and online resources.  

Comments are closed.

Skip to content